Time and Work

intermediate time and work work rate lcm method pipes cisterns efficiency

Time and Work problems look complicated, but there’s a single trick that makes almost every problem a breeze: the LCM method. Once we learn it, we’ll wonder why anyone bothers with fractions at all.

The core idea is simple: Work = Rate × Time. If A can do a job in 10 days, then A’s rate is 1/10 of the job per day. When people work together, their rates ADD UP.

The Fraction Method (Traditional)

If A can finish work in a days, A does 1/a of the work per day. If A and B work together, combined rate = 1/a + 1/b per day. Time to finish together = 1/(1/a + 1/b) = ab/(a+b).

This works, but dealing with fractions gets messy fast. Enter the LCM method.

The LCM Method — The Game Changer

Instead of working with fractions, we assume the total work is a concrete number — specifically, the LCM of the given times. This turns everything into whole numbers. WAY faster.

LCM Method — Steps
1. Find the LCM of all given times → this is our "total work units"
2. Divide total work by each person's time → their "efficiency" (units/day)
3. Add/subtract efficiencies as needed
4. Time = Total work / Combined efficiency
Key Formulas
A and B together: Time = ab/(a+b) days
A, B, and C together: Total work (LCM) / (efficiency_A + efficiency_B + efficiency_C)
If A is x times as efficient as B, and B takes 'd' days, then A takes d/x days
Pipes (inlet): positive efficiency
Pipes (outlet/leak): negative efficiency

Example 1: Basic LCM method

A can do a job in 12 days, B can do it in 18 days. How long to finish together?

LCM of 12 and 18 = 36 (this is our total work)

  • A’s efficiency = 36/12 = 3 units/day
  • B’s efficiency = 36/18 = 2 units/day
  • Combined = 3 + 2 = 5 units/day
  • Time = 36/5 = 7.2 days (or 7 days and 4.8 hours)

Compare with the fraction method: 1/12 + 1/18 = 3/36 + 2/36 = 5/36, time = 36/5 = 7.2 days. Same answer, but the LCM method feels more natural with whole numbers.

Example 2: Three workers

A, B, and C can do a job in 10, 15, and 20 days respectively. How long if all three work together?

LCM of 10, 15, 20 = 60 units.

  • A = 60/10 = 6 units/day
  • B = 60/15 = 4 units/day
  • C = 60/20 = 3 units/day
  • Combined = 6 + 4 + 3 = 13 units/day
  • Time = 60/13 = 4 and 8/13 days (approximately 4.6 days)

Example 3: One worker leaves midway

A and B together can finish a job in 12 days. They work together for 8 days, then B leaves. A finishes the remaining work in 10 more days. Find how long A and B individually take.

Let A’s time = a days, B’s time = b days.

Together: 1/a + 1/b = 1/12 … (i)

In 8 days together, they finish 8/12 = 2/3 of the work. Remaining = 1/3.

A finishes 1/3 in 10 days, so A’s rate = (1/3)/10 = 1/30. Thus a = 30 days.

From (i): 1/30 + 1/b = 1/12 → 1/b = 1/12 - 1/30 = (5-2)/60 = 3/60 = 1/20. Thus b = 20 days.

Alternate Day Work

Sometimes A works on day 1, B works on day 2, A works on day 3, and so on.

The trick: find the combined work done in a 2-day cycle, then figure out how many complete cycles are needed.

Example 4: Alternate day work

A can do a job in 10 days, B in 15 days. They work on alternate days, starting with A. When will the work be finished?

LCM of 10 and 15 = 30 units.

  • A’s efficiency = 3 units/day
  • B’s efficiency = 2 units/day

In a 2-day cycle (A then B): 3 + 2 = 5 units done.

After 10 days (5 complete cycles): 5 × 5 = 25 units done. Remaining = 30 - 25 = 5 units.

Day 11 (A’s turn): A does 3 units. Remaining = 5 - 3 = 2 units.

Day 12 (B’s turn): B does 2 units. Remaining = 0. Done!

Work finishes on day 12.

Pipes and Cisterns

Think of it like this: inlet pipes do “positive work” (filling the tank), and outlet pipes/leaks do “negative work” (emptying the tank). Everything else is the same as time and work.

Example 5: Pipes problem

Pipe A fills a tank in 12 hours, pipe B fills it in 15 hours, and pipe C empties it in 20 hours. If all three are opened, how long to fill the tank?

LCM of 12, 15, 20 = 60 units.

  • A fills: 60/12 = +5 units/hour
  • B fills: 60/15 = +4 units/hour
  • C empties: 60/20 = -3 units/hour

Net rate = 5 + 4 - 3 = 6 units/hour

Time = 60/6 = 10 hours

Example 6: Leak problem

A pipe fills a tank in 6 hours. Due to a leak, it takes 8 hours. How long would the leak alone take to empty the full tank?

LCM of 6 and 8 = 24 units.

  • Pipe rate = 24/6 = 4 units/hour
  • Net rate (pipe + leak) = 24/8 = 3 units/hour
  • Leak rate = 4 - 3 = 1 unit/hour (draining)

Time for leak to empty = 24/1 = 24 hours

Efficiency-Based Problems

“A is twice as efficient as B” means A’s rate is 2 times B’s rate. If B takes 20 days, A takes 10 days.

“A is 50% more efficient than B” means A’s rate is 1.5 times B’s rate. If B takes 30 days, A takes 30/1.5 = 20 days.

Example 7: Efficiency problem

A is 60% more efficient than B. If B can do a job in 40 days, how long do they take together?

A’s time = 40/1.6 = 25 days.

LCM of 25 and 40 = 200 units.

  • A = 200/25 = 8 units/day
  • B = 200/40 = 5 units/day
  • Combined = 13 units/day
  • Time = 200/13 = 15 and 5/13 days (approximately 15.38 days)

Common Exam Variations

  • A and B work together, one leaves partway — find individual times.
  • Alternate day work — who finishes and on which day?
  • Pipes and cisterns with multiple inlets and outlets.
  • “A does half the work, then B finishes the rest.”
  • Efficiency ratios: “A is x times as efficient as B.”
  • “If 5 men can do it in 10 days, how many men needed for 5 days?” (Use: Men × Days = constant)
  • MDH formula: M₁ × D₁ × H₁ = M₂ × D₂ × H₂ (Men × Days × Hours = constant work)

The MDH Formula

When the work stays the same:

M₁ × D₁ × H₁ = M₂ × D₂ × H₂

This means: if 5 men working 8 hours/day finish in 10 days, how many men are needed working 10 hours/day to finish in 4 days?

5 × 10 × 8 = M₂ × 4 × 10 → M₂ = 400/40 = 10 men

Practice Problems

Problem 1: A can do a job in 20 days, B in 30 days. They start together, but A leaves after 5 days. How many more days does B take to finish?

Problem 2: Two pipes can fill a tank in 10 and 12 hours. A drain pipe can empty it in 20 hours. If all three are opened, how long to fill the tank?

Problem 3: 12 men can finish a job in 16 days working 8 hours/day. How many men are needed to finish the same job in 12 days working 10 hours/day?


Answers

Problem 1: LCM of 20 and 30 = 60 units. A = 3/day, B = 2/day. In 5 days together: 5 × (3+2) = 25 units done. Remaining = 60 - 25 = 35 units. B alone: 35/2 = 17.5 more days.

Problem 2: LCM of 10, 12, 20 = 60 units. Pipe 1 = +6, Pipe 2 = +5, Drain = -3. Net = 8 units/hour. Time = 60/8 = 7.5 hours.

Problem 3: M₁D₁H₁ = M₂D₂H₂ → 12 × 16 × 8 = M₂ × 12 × 10 → M₂ = 1536/120 = 12.8, so 13 men (round up since we can’t have partial men).